Avdiivka Coke (AKHZ) has completed the overhaul of engineering networks in basements of ten high-rise buildings hit most by the hostilities. To this end, Metinvest Group channelled over UAH 3.5 million.
According to utility companies, the heating system of building No.4 on Semashko Street, buildings No. 14, 15-15а, 18, 21 and 27 in the 9th residential quarter and buildings No. 4, 5, 7 and 27 on Karla Marksa Street was in very poor condition and urgently needed repairing. The buildings could have lost heating at any time.
AKHZ decided to take actions to prevent the accident. The plant replaced old pipes with plastic ones and installed stop valves.
“All our services were working hard to finish repair works as soon as possible and prevent the risk of leaving about two thousand people without the heating at the most inappropriate moment,” said AKHZ CEO Musa Magomedov.
On the initiative of Rinat Akhmetov, Avdiivka Coke repaired 15 social facilities, 69 residential buildings and 135 private houses in 2015. Investments made UAH 18 million.
Source: Metinvest CSR-portal